Madras High Court restrains thermal power plant workers from going on strike
The Hindu

The Madras High Court issued an interim injunction restraining thermal power plant workers from proceeding with a proposed strike.
Justices S.M. Subramaniam and R. Rajesh Vivekananthan of the Madras High Court granted an interim injunction against thermal power plant workers. The court action came in response to a public interest litigation (PIL) petition filed to challenge the proposed strike. The ruling legally blocks the workers from executing the strike while the petition is addressed.